Oneida Steet - Skyline Bridge to Midway Road

Print
Press Enter to show all options, press Tab go to next option

PROJECT DESCRIPTION:

PROJECT 6: 

  • A DOT/City of Appleton project which involves the reconstruction of the concrete pavement along Oneida Street from the Skyline Bridge to north of Roeland/Valley Road.  Also included, is the reconstruction of concrete pavement on Olde Oneida Street from Oneida Street to E South River Street and on Calumet Street from west of Oneida Street to Jefferson Street. 
  • Plan and Profile sheets
  • Traffic Control and Staging sheets

Weekly Update

  • Schedule: tentative April 2018 to November 2018
  • Contractor: Vinton Construction - Jerry Franklin 920-374-0786

PROJECT 7:

  • A DOT project which involves the reconstruction of concrete pavement at the intersection of Oneida Street and Roeland/Valley Road.
  • Schedule: spring 2018

PROJECT 8:

  • A DOT project which involves the construction of a diverging diamond interchange at Oneida Street and STH 441.
  • Schedule: Fall of 2018