Oneida Steet - Skyline Bridge to Midway Road

Print
Press Enter to show all options, press Tab go to next option

PROJECT DESCRIPTION:

There will be multiple projects over multiple years on Oneida Street from the Skyline Bridge to Midway Road.  The multiple projects are detailed below.  Also, in addition to the projects listed below, private utility companies such as WE Energies, AT&T, Charter Communications, and the Village of Fox Crossings will be relocating their infrastructure as well such as power poles, electric lines and gas lines.

2017

PROJECT 1:  

  • A City of Appleton project which involves the reconstruction of sanitary sewer, storm sewer and water main along Oneida Street from the Skyline Bridge to Calumet Street.  Also included in this project is Olde Oneida Street from Oneida Street to E South River Street, Lincoln Street from Olde Oneida Street to Madison Street and Calumet Street from Oneida Street to Jefferson Street.  The final new road surfaces will be constructed in 2018.
  • Scheduled to start in March of 2017 and be complete by October of 2017.
  • Tentative construction phasing: Overall phasing
  • Plan Set
  • City of Appleton contact:  Randey Felton, randey.felton@appleton.org, 832-6483
  • Contractor: Kruczek Construction

PROJECT 2:

  • A City of Appleton project which involves the reconstruction of sanitary sewer, storm sewer and water main along Oneida Street from Calumet Street to Midway Road. The final new road surface will be constructed in 2018.
  • Scheduled to start in March of 2017 and be complete by October of 2017.
  • Tentative construction phasing: Overall phasing
  • Construction Schedule
  • Plan Set
  • City of Appleton contact: Mark Kilheffer, mark.kilheffer@appleton.org, 832-6327
  • Contractor: Dorner Inc

PROJECT 3:

  • A DOT project which involves the reconstruction of new concrete pavement at the intersection of Oneida Street and Midway Road.  The limits of this project are about 500' in each direction.
  • Scheduled to start in August of 2017
  • DOT contact: Scott Ebel, 920-492-5676

PROJECT 4:

  • A DOT project which involves concrete repair and replacement, asphalt pavement milling, asphalt pavement resurfacing, curb and gutter repair at spot locations, concrete sidewalk and curb and gutter and curb ramp upgrades at intersections, storm sewer inlet repair and new storm sewer, signal upgrades, signing, and pavement marking on Oneida Street from south of Midway Road to STH 114.
  • Scheduled to start in August of 2017 and be complete by October of 2017.
  • DOT contact: Scott Ebel, 920-492-5676

PROJECT 5:

  • A DOT project which involves the widening of the STH 441 bridge piers on Oneida Street.
  • Scheduled to start in June of 2017
  • DOT contact: Scott Ebel, 920-492-5676 

2018

PROJECT 6: 

  • A DOT/City of Appleton project which involves the reconstruction of the concrete pavement along Oneida Street from the Skyline Bridge to north of Roeland/Valley Road.  Also included, is the reconstruction of concrete pavement on Olde Oneida Street from Oneida Street to E South River Street and on Calumet Street from west of Oneida Street to Jefferson Street. 
  • Schedule: tentative April 2018 to November 2018

PROJECT 7:

  • A DOT project which involves the reconstruction of concrete pavement at the intersection of Oneida Street and Roeland/Valley Road.
  • Schedule: 2018 construction

2019 or 2020

PROJECT 9:

  • A DOT project which involves the construction of a diverging diamond interchange at Oneida Street and STH 441.
  • Schedule: tentative